आया रे खिलौने वाला खिलौने लेकर आया रे..., मेमरीज़ ऑफ रफ़ी साहिब में सजी सुरों की महफिल CROSS-BORDER ARMS & EXPLOSIVES SUPPLY NETWORK BUSTED IN AMRITSAR; ONE HELD WITH AK-47 RIFLE, TWO HAND GRENADES  SOUTH WESTERN AIR COMMAND ORGANISES SEKHON IAF MARATHON 2026 DELHI EOW ARRESTED ACCUSED INVOLVED IN FORGED GOV DOCUMENTS ARRESTED AFTER MULTI-STATE TRACKING  MANKIND PHARMA CONTRIBUTED RS. 1 CRORE TO BRAVO CAPTAIN SMIT MACHCHHAR, SAVING LIVES OF PASSENGERS HIMACHAL RESIDENT SENTENCED TO 10 YEARS RIGOROUS IMPRISONMENT, PROCURING DRUGS FROM UK, FRANCE AND GERMANY THREE VEHICLES BURNT AT A EUNUCH’S DERA NEAR SADULSHEHAR; GOLD AND CASH MISSING THE CHIEF ELECTION COMMISSIONER SHOULD RESIGN:-KUMARI SELJA NO COMPROMISE ON CONSTITUTIONAL RIGHTS OF MERIT AND RESERVATION:-KUMARI SELJA
Punjab Trending

DECKS CLEAR FOR DISBURSEMENT OF COMPENSATION & POSSESSION OF LAND FOR RUPNAGAR-LUDHIANA WITH SPUR to KHARAR SECTION OF NH-205K

Read in:English

CHIEF SECRETARY ASKS DCs TO EXPEDITE HANDING OVER POSSESIONS TO NHAI

Face2News/Chandigarh 

With concerted efforts of Chief Minister Bhagwant Mann, the State Government has received a communication from Ministry of Road Transport and Highways for disbursement of compensation & possession of encumbrance free land for all packages of Ludhiana-Rupnagar with Spur to Kharar section of NH-205K.

In a meeting held today under the Chairmanship of Chief Secretary Vijay Kumar Janjua regarding land acquisition of Ludhiana-Rupnagar highway, it was informed that decks have been cleared for disbursement and possession of land for the project. The Chief Secretary Mr Janjua also directed Deputy Commissioners to expedite handing over of possession of land for all National Highway projects as these are going to boost economy of the State.(SUBHEAD)

Secretary, Public Works (B&R) Nilkanth S Avhad apprised that a communication from Secretary MORT&H had been received and asked to expedite the work.

Taking part in deliberations, Deputy Commissioner Ludhiana Surbhi Malik mentioned that District Administration was making continuous efforts to take possession of land. Under Package-I, possession of 18.90 Km out of 37.70 Km has already been taken. DC, Ludhiana further mentioned that within next week 70% possession of land will be handed over to NHAI. Subsequently, possession of land under Package-II will be taken.

Similarly, the Deputy Commissioner Rupnagar Preeti Yadav also stated that under Package-III, possession of 13 Km out of 36.26 Km had already been handed over to NHAI. It was further brought out that 80% of land will be handed over by next week. The Deputy Commissioner SAS Nagar Amit Talwar mentioned that under Package-III, 80% of land will be handed over by the next week.

Meanwhile, Chief Secretary asked NHAI representatives to mobilise full resources on site with more manpower and machinery.